Register of completed embedded generation projects

The following is a register of completed embedded generation (EG) projects connected to Ausgrid's network. This register was established on 1 October 2014 and is updated annually in December. It provides information for connections made under the Chapter 5 connection process (for connections made in the past 5 years) and the Chapter 5A connection process (for connections made since 1st March 2015) in the National Electricity Rules.

The register includes where relevant and available, details of the plant technology, maximum power capacity, contribution to fault levels, size and rating of the relevant transformer, single line diagram, protection and communication systems, and voltage control and reactive power capability. 

Large projects >5MW - last five years

 Projects
 Connection Date
(click to download report)
 Glenbawn Hydro Power Station  31-Jul-12


Small projects <5MW - 1st Mar 2015 to 1st Dec 2015

Projects Connection Date
(click to download report)
North Turramurra Golf Course STP
29-Sep-15
Col Crawford Pty Ltd
01-Sep-15
Eastern Distributor Woolloomooloo
20-July-15
Gilbarco Australia
25-Jun-15
Kass Group Pty Ltd
23-Jun-15
Central Coast Group Training
22-Jun-15
Pittwater RSL
15-Jun-15 
Tyrrells Winery Pokolbin
10-Jun-15 
Foghorn Brewhouse
01-Jun-15
Tefco Engineering
29-May-15
Exus Hub
25-May-15
Golden Highway Merriwa
05-May-15
 Clean Plus Chemicals 
05-May-15
 Thomas Holt Drive
 28-Apr-15
BMW Brookvale
30-Mar-15
 Heng Fai Trading Pty Ltd
18-Mar-15
1/14 Mildon Rd Tuggerah
06-Mar-15