Lake Munmorah power upgrade

Ausgrid has constructed a new substation to serve homes and businesses in Lake Munmorah and surrounding areas. The new substation is located on the corner of Carters Road and the Pacific Highway in Lake Munmorah, adjacent to the former zone substation that has been retired from service.

The project is required to allow Ausgrid to maintain a reliable power supply to the area.

Two new 132,000 volt power lines were constructed to power to the new new substation, one from Munmorah bulk supply point and the other from Vales Point bulk supply point.

The new substation was commissioned in November 2012.