Information pack: non-micro embedded generators


This information pack applies to embedded generator (EG) connections that will follow the connection process regulated by Chapter 5A of the National Electricity Rules (NER), excluding those defined as micro-embedded generators. This process generally applies to generators with a capacity ranging from 30kW to 5MW that will not be registered with the Australian Energy Market Operator (AEMO).

A number of documents are included as part of this pack, accessible via the links in the drop down list below. The Non-Registered Embedded Generator Guideline provides a directory to these documents.