SER planning process

Follow the six-step process to complete Ausgrid's NS174A SER.
 

Ausgrid is required by law to assess the environmental impacts of proposed infrastructure and ensure all necessary approvals, licences and permits are obtained. The steps below outline the process for preparing, assessing and verifying an NS174A Summary Environmental Report (SER) under Part 5 of the EP&A Act.

Six steps to complete Ausgrid's NS174A SER

The biggest cause of project approval delays is failing to define the scope of works upfront. The scope determines what approvals are needed, how impacts are assessed, and which activities are approved by the SER. A poorly worded scope may restrict what activities can occur, while late changes may require re-notifying council and cause 21–40 day delays.

Attach design drawings and clearly confirm any works not included in the scope.

SER FAQs

A SER under Part 5 of the EP&A Act does not technically expire. However, because conditions can change, the following applies:

  • If 2 years have passed since verification and construction has not started, the SER must be reviewed (GIS report, site inspection, and—if a new substation—re-notification of adjoining occupants).
  • If 5 years have passed with no construction, the SER must be withdrawn and redone.

Permits and approvals may have their own expiry dates, which should also be checked.

Yes. Any exceptions must be approved by the Manager – Environmental Services and would only be granted in exceptional circumstances. Assessors are encouraged (but not required) to use the EF 17410 SER Site Inspection Checklist.

Yes, as long as the scope of works is clearly described, including:

  • substation locations,
  • streets with 11kV/415V cabling,
  • easements, vegetation removal, and access tracks.

If locations are uncertain, include a broader area to cover possible options. Plans should show enough detail to assess impacts. Where details are missing, assume the worst-case scenario.

If the scope changes significantly (e.g. Aboriginal heritage is identified), a new SER may be required. Any later works not consistent with the original scope will need a separate SER.

Yes, provided the works are fully described in the approval (substations, cabling routes, easements, vegetation removal, access tracks). Written confirmation is required from the determining authority or developer that the works are covered.

No. However, any works or impacts outside the approved scope must be assessed in the SER.

  • The ASP must provide Ausgrid with the relevant development approval.
  • The SER should include a condition that no works commence until the site is cleared in accordance with that approval.

Yes, if the reports cover the footprint and impacts of the electricity works (including easements and access tracks). Include the reports in the SER and capture any relevant conditions.

Yes, if the changes alter:

  • route alignment, asset location, scale, or purpose of the works,
  • potential environmental impacts, or
  • introduce new impacts not covered by the existing SER.

The review should be documented by the assessor and sent to the verifier to update project records.

Notification FAQs

Preferably yes, to ensure submissions are received and considered. Exceptions include:

  • emergency works to restore power,
  • Council confirms no further submissions will be made, or
  • Council requests the works proceed.

Any other exceptions require Manager – Environmental Services approval.

Re-notification is required if changes:

  • trigger new notification requirements (e.g. new adjoining neighbours), or
  • result in a substantially different project or potential new objections.

To avoid re-notification, concept plans should describe all potential works and may include options and a larger footprint for flexibility.

Exempt development does not require 21-day notice under SEPP (Transport and Infrastructure) 2021, but still requires 40-day notification under the Electricity Supply Act unless it is routine maintenance or repairs.

Most urgent works will fall under "emergency works" or "routine maintenance/repairs" and will not require a SER or notification.

Use Ausgrid’s standard notification letter templates.

Looking for something else?

Other useful resources

Environmental planning documentsSER TrainingPlanning updates