Guide to HV Live Work Design Principles
NS214: Guide to HV Live Work Design Principles
This Network Standard identifies the factors that should be taken into account by designers of overhead mains to facilitate the application of HV Live Work on Ausgrid’s network. The designer must balance these issues with construction costs, the requirements of other Ausgrid Network Standards, and any job-specific design instructions issued by the local Ausgrid office, identifying the desired outcomes of the specific project.
Scope
This guideline applies to the design of overhead mains to facilitate the use of HV Live Work methods. Design for use of HV Live Work methods is only to be carried out during projects driven through maintenance or construction programs. Poles are not to be replaced just to facilitate use of HV Live Work Methods.