Concord substation upgrade

In progress. 

Building a new switchroom, east of the existing substation, adjacent to the Sydney Trains T9 Northern Railway Line.

Two Ausgrid field workers with newly installed Siemens SF6 switchgear.
Two Ausgrid field workers with newly installed Siemens SF6 switchgear.

Project overview

Ausgrid is planning to build a new switchroom on Ausgrid land, east of the existing substation, adjacent to the Sydney Trains T9 Northern Railway Line. 

The work will involve: 

  • constructing a new switchroom building
  • installing new switchgear and associated equipment within the new building
  • minor internal and external repairs of the existing building; excavating and trenching to install underground cables and electrical connections
  • decommissioning and removing existing switchgear. Please take a look at the newsletter at the bottom of this page, which shows the proposed location of the new building and underground connections.

Timeline

1

March-April 2020

Concept planning and obtaining community and stakeholder feedback.

2

April-May 2020

Review of Environmental Factors preparation and display

3

Late-2021 to early-2022

Engage civil contractor, early works along southern driveway and transformer replacement.

4

Early-2022 to mid-2022

Northern driveway works

5

Mid 2022 to early-2023

Construction of the new switchroom

6

Early 2023 to late 2023

Installation of equipment inside new switchroom building

7

Early-2024 to late 2025

Works to make connections to the surrounding network and staged transformer replacements.

Building design 

Based on the community’s feedback, a final design has been selected for the switchroom. 

In considering the visual impact on the surrounding community, the building has been designed to reflect the local area. 

The proposed exterior materials are precast concrete panels, coated with a high bond strength paint. The neutral pastel colours complement the residential and commercial neighbourhood. This finish will provide superior weatherproofing for the building. The roof will be clad with high-grade Colorbond roof sheeting. 

The final design can be viewed via a link at the bottom of this page

Project approval process and environmental assessment

Under the State Environmental Planning Policy, Ausgrid is the approving authority for the project. As part of the approval process, Ausgrid undertake an environmental assessment. Review of Environmental Factors (REF), to investigate the potential environmental impacts associated with the project. The REF has now been finalised and the project has been approved for construction.

Review of environmental factors (REF)

If you have any questions about any of the issues raised in the REF, please let us know. 

Community consultation

Ausgrid has received feedback from the community on this project and incorporated this into designs for the new switchroom and the Review of Environmental Factors (REF). The final design and finalised REF can be viewed via a link at the bottom of this page. 

Your feedback and enquiries are welcome at all stages of the project to ensure we are effectively managing any impacts on the immediate community.

How this work may affect you

Like on any construction site, issues such as noise and dust, as a result of work on and around the site, will be carefully managed. 

Ausgrid works hours are 7am to 6pm on weekdays, and 8am to 1pm on Saturdays, with no work on Sundays or public holidays. We will notify nearby neighbours in advance of thethe  work that will take place outside of these hours. 

Please note that the Concord substation will remain in service for the duration of the project. Normal day-to-day operations will continue to maintain electrical supply.

Related documents

Main document

Frequently Asked Questions

pdf
0.19MB

Looking for something else?